Ofgem details proposals to remove speculation from the demand connections queue

techUK has been working closely with Ofgem, NESO and Government since late 2025 on demand connections reform - a process that aims to remove speculative applications from the significantly inflated queue to connect to the grid, while ensuring viable, strategically important projects see much shorter waiting times.  

Ofgem has now (July 2026) published the long-awaited Curate - Demand Connections Reform consultation, setting out its proposed next steps. Curate is the first of three pillars of reforms, aiming to deter speculative developers from holding capacity without overly burdening viable projects. These reforms are urgent, as the queue - which now includes 73GW of data centre applications across transmission and distribution - is arguably the most significant barrier to data centre development in the UK. techUK has consistently argued that the majority of these projects will never see energisation and must be removed.  

Ofgem sets out two main proposals as part of Curate: 

  • The introduction of a financial mechanism 
  • The addition of data centre-specific Gate 2 readiness requirements on top of existing connection milestones  

Financial mechanism  

The consultation proposes a commitment fee value for projects above a 40 MW threshold in the range of £237,500/MW to £712,500/MW, which represents around 2.5% to 7.5% of an average data centre project’s CapEx of £9,500,000/MW. For example, a 100MW data centre would have to secure £23.8 million to £71.3 million at the point of accepting a connection offer and have it returned at energisation. If the project is terminated, this amount will be paid in full.  

Ofgem's reasoning for setting the fee so high is that similar financial mechanisms in other jurisdictions have not worked, and it considers CapEx more appropriate than DeEx as it scales to size. The logic behind the 40MW threshold is that smaller developers should not be unfairly burdened and that 99% of total capacity in the queue will still be captured by this fee. 

Gate 2 readiness requirements 

Ofgem plans to introduce three new termination milestones at different stages for data centres only. These would cover projects of 10MW and above, connected at both transmission and distribution, and apply slightly differently based on whether developers take the "self-operation" pathway or "lease or sale" pathway. Ofgem notes that stage 1 is forward dating while stages 2 and 3 are backward dating, like the existing queue milestones as part of TMO4+, and that the compute offtaker requirement at M0.5 Dc is non-binding whereas by M6. Dc it is binding. 

  1. Stage 1 (M0.5 Dc): Compute offtaker – applied at 6 months post-connection offer.  
  2. Stage 2 (M2 Dc): Long-lead procurement (electrical equipment) – applied at M2.  
  3. Stage 3 (M6 Dc): Technical capability, financial capability, customer contract ("lease or sale" pathway only) – applied at M6.  

Other originally proposed readiness requirements:  

  • Flexibility: this has been ruled out and now sits with Connect Operate. 
  • Planning: this has been ruled out. 
  • Developer track-record test: this has been ruled out as it could create barriers to entry for new market participants. 
  • Look-back test: whilst not included in this consultation, Ofgem notes the proposed milestone regime could establish an evidence base that informs future consideration of developer behaviour and project progression. 

The techUK view 

Reforming the queue is vital to sustaining a healthy UK data centre sector and we welcome Ofgem’s significant work on this pressing issue. Readiness requirements will help to ensure only viable projects progress and it is positive to see some of our recommendations, e.g. financial capability and the look-back test, under consideration.  

Whilst we are strongly supportive of a financial mechanism, the extremely high commitment fee in this consultation is a significant area of concern and risks making the UK far less attractive as an investment destination for data centres. Maintaining pace in the global AI and digitalisation race will not be achieved through burdensome costs such as these.

We will be making the case for a more proportionate, yet still effective, approach. Get in touch with the team below to have your say:

Katie Davies

Katie Davies

Head of Energy and Infrastructure Policy, techUK

Luisa C. Cardani

Luisa C. Cardani

Head of Data Centres Programme, techUK

 Jade van Zuydam

Jade van Zuydam

Junior Programme Manager - Energy and Utilities, techUK


Data Centres Programme activities

techUK provides a collective voice for UK Data Centre operators working with government to improve the business environment for our members. We keep members up to date with the key technical and regulatory developments that may impact growth and on funding opportunities that may increase commercial competitiveness. Visit the programme page here.

 

Upcoming events

Latest news and insights 

Learn more and get involved

 

Data Centres updates

Sign-up to get the latest updates and opportunities from our Data Centres programme.

 

 

 

Here are the five reasons you should join the Data Centres programme.

Learn about the value members get from our work.

Download

Join techUK groups

techUK members can get involved in our work by joining our groups, and stay up to date with the latest meetings and opportunities in the programme.

Learn more

Become a techUK member

Our members develop strong networks, build meaningful partnerships and grow their businesses as we all work together to create a thriving environment where industry, government and stakeholders come together to realise the positive outcomes tech can deliver.

Learn more

 

 Meet the team 

Luisa C. Cardani

Luisa C. Cardani

Head of Data Centres Programme, techUK

 Jade van Zuydam

Jade van Zuydam

Junior Programme Manager - Energy and Utilities, techUK

Lucas Banach

Lucas Banach

Programme Assistant, Data Centres, Climate, Environment and Sustainability, Market Access, techUK